Tool

Particulate Monitoring

A web tool for tracking airborne particulate during healthcare construction projects. It stores particle counter readings by monitoring location, compares construction-phase readings to the pre-construction baseline and to outside air, and produces the records a facility needs for its infection control documentation.

Method

The monitoring method the tool supports

1

Before construction: baseline

At each monitoring location, collect baseline readings on 4 separate days with a particle counter. Take each reading in the breathing zone and at the supply diffuser, and record an outside air reading on the same day.

2

During construction: weekly readings

Take readings at the same locations once a week for the duration of the project. Each reading is compared to that location's baseline and to the outside air reading for the same date.

3

Review and report

The tool shows how each location is trending over time, flags readings that exceed defined multiples of baseline, and exports the project record as PDF or CSV for infection control committee review.

What the tool calculates

Comparisons across six particle size channels

For every reading, the tool calculates the ratio to the location baseline and the ratio to outside air in each of the six size channels reported by a standard particle counter. Readings are flagged when a channel reaches 1.5 times, 2 times, or 3 times its baseline value.

  • Baseline average per location, per channel, from the 4 baseline days
  • Weekly reading compared to baseline and to outside air
  • Flags at 1.5x, 2x, and 3x of baseline
  • Email alerts when a flag threshold is reached
  • Trend charts per location over the life of the project
  • PDF and CSV report exports
Size channels (µm)
0.3
0.5
1.0
2.0
5.0
10.0
Flag thresholds
1.5x baseline2x baseline3x baseline

A particle counter is required to use the tool and is not included with a subscription.

Plans

Plans and pricing

All plans are billed yearly. Contractor project slots are reusable when a project is completed, completed projects remain viewable, and read-only guest access for hospital staff is included.

For hospitals

Facility

$1,500per year, per facility
Unlimited projects at that facility
  • Covers every construction project at one facility
  • Baseline and weekly readings for each monitoring location
  • PDF and CSV report exports
Request access
For contractors

Contractor Standard

$1,500per year
Up to 3 active projects at the same time
  • Project slots are reusable when a project is completed
  • Completed projects remain viewable
  • Read-only guest access for hospital staff included
Request access
For contractors

Contractor Plus

$3,500per year
Up to 10 active projects at the same time
  • Project slots are reusable when a project is completed
  • Completed projects remain viewable
  • Read-only guest access for hospital staff included
Request access

More than 10 active projects: contact Oncore for pricing.

Existing subscribers: Log in.

Online subscription is not yet open. Request access and our team will set up your account.